... | ... | @@ -15,7 +15,7 @@ FPGA. |
|
|
|
|
|

|
|
|
|
|
|
*AFC production board** - ([Top
|
|
|
**AFC production board** - ([Top
|
|
|
view](https://www.ohwr.org/project/afc/uploads/28ef8b39ac0952926931bef84a25d8d5/AFC_TOP_v3_1.JPG), [Bottom
|
|
|
view](https://www.ohwr.org/project/afc/uploads/5372faa7cec5cbc101eb8f5c0f0cfa8a/AFC_BOT_V3_1.JPG))
|
|
|
|
... | ... | @@ -64,8 +64,7 @@ view](https://www.ohwr.org/project/afc/uploads/5372faa7cec5cbc101eb8f5c0f0cfa8a/ |
|
|
|
|
|
### Commercial producers
|
|
|
|
|
|
- [Creotech](http://creotech.pl/product-scientific/amc-fmc-carrier-afc),
|
|
|
Poland
|
|
|
- [AMC FMC Carrier – AFC](http://creotech.pl/product-scientific/amc-fmc-carrier-afc) - [Creotech](http://creotech.pl), Poland
|
|
|
|
|
|
### General question about project
|
|
|
|
... | ... | @@ -81,11 +80,11 @@ view](https://www.ohwr.org/project/afc/uploads/5372faa7cec5cbc101eb8f5c0f0cfa8a/ |
|
|
|23-07-2012|Digital back-end for Sirus BPM schematics started. Creotech is in charge of the boards design.|
|
|
|
|12-09-2012|First version of schematics pushed to the repository.|
|
|
|
|24-09-2012|Proposal for cooling, carrier and backplane components placement.|
|
|
|
|09-11-2012|Project redefinition: backplane and enclosure will use MicroTCA.4 COTS hardware. The FPGA board should be an AMC board compliant with MTCA.4.|
|
|
|
|09-11-2012|Project redefinition: backplane and enclosure will use MicroTCA.4 COTS hardware.<br/>The FPGA board should be an AMC board compliant with MTCA.4.|
|
|
|
|1-04-2013|PCB finished.|
|
|
|
|29-04-2013|PCB assembled, still waiting for panels from ELMA.|
|
|
|
|29-05-2013|PCIe works, SDRAM works, clocks work.|
|
|
|
|8-09-2013|Next production batch (10 pieces) of the board started. Applied several cosmetic changes but 100% backward compatibility is preserved.|
|
|
|
|8-09-2013|Next production batch (10 pieces) of the board started. Applied several cosmetic changes <br/>but 100% backward compatibility is preserved.|
|
|
|
|01-10-2013|Batch of 10 pcbs delivered|
|
|
|
|01-11-2013|All boards up and running|
|
|
|
|20-03-2014|Version 3 with RTM ready for production|
|
... | ... | |