... | ... | @@ -60,7 +60,7 @@ Advantages of standardization: |
|
|
Standardization is a considerably long process that can be approached in
|
|
|
various ways and from various directions. Potential paths (see
|
|
|
[presentation](https://www.ohwr.org/project/white-rabbit/uploads/b5d237adf2198f9da783fd44e87c4eeb/ITU-T_meetingReport.pdf))
|
|
|
for WR's standardization had been identified. These include:
|
|
|
for WR's standardization had been identified. These included:
|
|
|
|
|
|
- [Standardization at the International Telecommunication Union-
|
|
|
Telecommunication Standardization Sector
|
... | ... | @@ -114,20 +114,23 @@ Protocol. |
|
|
|
|
|
## Project plan
|
|
|
|
|
|
1. \_[White Rabbit Standardization Group](std-group)_ established (the
|
|
|
end of April 2012):
|
|
|
- representatives of Scientific Institutes (e.g. CERN, GSI) and
|
|
|
companies (e.g. NI)
|
|
|
- members of WR Collaboration and external experts
|
|
|
- the responsibility of the group is to perform the further
|
|
|
actions
|
|
|
2. Each potential path for WR standardization needs to be identified,
|
|
|
studied and evaluated
|
|
|
3. The most suitable path (in terms of costs, efforts, time) decided
|
|
|
(the end of 2012)
|
|
|
4. The standardization effort started (February 2013)
|
|
|
5. An official standardization of White Rabbit will mark the end of the
|
|
|
project
|
|
|
1. Evaluation of standardization path/method
|
|
|
1. \_[White Rabbit Standardization Group](std-group)_ established
|
|
|
to help in evaluation (the end of April 2012):
|
|
|
1. representatives of Scientific Institutes (e.g. CERN, GSI)
|
|
|
and companies (e.g. NI)
|
|
|
2. members of WR Collaboration and external experts
|
|
|
3. the responsibility of the group is to perform the further
|
|
|
actions
|
|
|
2. Each potential path for WR standardization needs to be
|
|
|
identified, studied and evaluated
|
|
|
3. The most suitable path (in terms of costs, efforts, time)
|
|
|
decided (the end of 2012)
|
|
|
2. Standardization of White Rabbit within
|
|
|
[P1588](https://ieee-sa.centraldesktop.com/1588public/)
|
|
|
1. The standardization effort started (February 2013)
|
|
|
2. An official standardization of White Rabbit will mark the end of
|
|
|
the project
|
|
|
|
|
|
## Project's timeline
|
|
|
|
... | ... | |