## Veryx Tests
|
|
|
|
|
|
We use [Veryx ATTEST PTP Conformance Test Suite](https://www.veryxtech.com/wp-content/uploads/2017/03/ATTEST-CTS_PTP_Datasheet.pdf) to perform regression tests of WR Switch releases. Out of 87 tests grouped into 6 groups, we have selected tests cover the features implemented by the WR Switch. These test groups are:
|
|
|
- Message Format Group (MFG)
|
|
|
- Message Handling Group (MHG)
|
|
|
- Message Transaction Group (MTG)
|
|
|
- PTP BMC Election Group (BEG)
|
|
|
- PTP Configuration Group (PCG)
|
|
|
- STATE MACHINE GROUP (SMG)
|
|
|
The tests that we expect the WR Switch to pass are listed below. There is a number of tests that do not pass due to known bugs, these are listed below as well.
|
|
|
|
|
|
## Tests that a release must pass (65 tests for IEEE802.3 and 65 tests for UPD mapping)
|
|
|
|
|
|
| TEST Name | Test Purpose Description | v5.0.1| v6.0 |
|
|
|
| --------- | ------ |--------- | ------ |
|
|
|
|BEG_001 |Verify that a boundary clock is elected as the Master based on Priority1. | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | |
|
|
|
| | | | | |
|
|