... | ... | @@ -135,7 +135,8 @@ board*](https://www.ohwr.org/project/spec/wiki). Click the picture for a detaile |
|
|
## Project information
|
|
|
|
|
|
- Official production documentation
|
|
|
- [Schematics](https://www.ohwr.org/project/spec7/wikis/uploads/4d695283eafd4415de920bd07f5fac6d/SPEC7_Abracon_Powered_190814.pdf) (Note: Design created with Mentor Graphics using a Xpedition).
|
|
|
- [Schematics](uploads/bf937ca0417870544f98a33bdc487e8e/11300.01.05.2_SCH.PDF) (Note: Design created with Mentor Graphics using a Xpedition).
|
|
|
- [Manufacturing files 11300.01.05.2_SPEC7_v2.zip](uploads/aedb2b93a9987ac9989d4f57e6c6a404/11300.01.05.2_SPEC7_v2.zip) (Note: PCB Design created with Mentor Graphics using a Xpedition License)
|
|
|
- Design Specification
|
|
|
- [Specification gathering discussion](specgather) - a list of
|
|
|
wish items ...
|
... | ... | @@ -196,8 +197,8 @@ board*](https://www.ohwr.org/project/spec/wiki). Click the picture for a detaile |
|
|
| 19-08-2019 | Planning: 2 boards production & assembly ready: Nov.2019. 10 boards production & assembly ready: Jan.2020
|
|
|
| 18-11-2019 | First two prototypes arrived.
|
|
|
| 10-12-2019 | Testing revealed a couple of minor issues and one major issue. A 2nd version PCB is needed.
|
|
|
| 20-01-2020 | Layout of V2 nears is finalized.
|
|
|
| 31-01-2020 | Layout of V2 finalized.
|
|
|
|
|
|
-----
|
|
|
|
|
|
24 January 2020 |
|
|
31 January 2020 |