... | ... | @@ -152,18 +152,22 @@ One assembled board will arrive in a week.</td> |
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>10-08-2011</td>
|
|
|
<td>New version of schematics ready. Will be reviewed on 16-08. DDR3 memory and DDS not debugged yet.</td>
|
|
|
<td>New version of schematics ready.</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>16-08-2011</td>
|
|
|
<td>Schematics design review held <a href="review16082011" class="uri">review16082011</a>. The design office will layout from 24 August on.</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>13-09-2011</td>
|
|
|
<td>Schematics still being updated. The design office will layout from 19 September on.</td>
|
|
|
</tr>
|
|
|
</tbody>
|
|
|
</table>
|
|
|
|
|
|
-----
|
|
|
|
|
|
Andrea Boccardi, Erik van der Bij - 26 August 2011
|
|
|
Andrea Boccardi, Erik van der Bij - 13 September 2011
|
|
|
|
|
|
|
|
|
|
... | ... | |