... | ... | @@ -155,16 +155,32 @@ Unchanged: |
|
|
<td>TE-ABT & BE-CO reviews finished</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>23-03-2016</td>
|
|
|
<td>Schematics transfer (v0.5) to CERN's Design Office for PCB routing</td>
|
|
|
<td>22-02-2016</td>
|
|
|
<td>PCB routing started by designer - focus on critical components</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>23-03-2016</td>
|
|
|
<td>Schematics & PCB transfer (v0.5) to CERN's Design Office for PCB routing</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>09-05-2016</td>
|
|
|
<td>PCB design finished, launch of prototype production (2x)</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>14-07-2016</td>
|
|
|
<td>First prototype available for testing</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>25-07-2016</td>
|
|
|
<td>Main components validated: Zynq PS & PL, DDR3, power supplies and sequencer</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>29-08-2016</td>
|
|
|
<td><em>Full board validated, implement 2nd iteration schematics & PCB</em></td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>30-06-2016</td>
|
|
|
<td><em>First prototype available for testing</em></td>
|
|
|
<td>12-09-2016</td>
|
|
|
<td><em>Order pre-series production (10x)</em></td>
|
|
|
</tr>
|
|
|
</tbody>
|
|
|
</table>
|
... | ... | |