... | ... | @@ -323,12 +323,12 @@ end May |
|
|
| 18-09-2020 | [Clocking FMC schematics review](https://ohwr.org/project/wr-switch-hw-v4/wikis/Clocking-FMC) |
|
|
|
| 16-11-2020 | [WR community feedback and its resolution](https://ohwr.org/project/wr-switch-hw-v4/wikis/Feedback-to-WRS-4-hardware-specification) |
|
|
|
| 19-11-2020 | [WRS-4 Hardware Specification](uploads/f6243e1cf7bc4fcde92e8e818fe461eb/WRS-4_Hardware_Specification-v1.1.pdf) published. It is based on previous feedback and used for the first prototype |
|
|
|
| 01-02-2021 | [Main board schematics review](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics) |
|
|
|
| 01-02-2021 | [Main board schematics review](https://ohwr.org/project/wr-switch-hw-v4/-/wikis/WRSv4-v1-Reviews) |
|
|
|
| 11-02-2021 | [Clocking FMC](https://ohwr.org/project/wr-switch-hw-v4/wikis/Clocking-FMC) delivered to CERN |
|
|
|
| 11-04-2021 | [Enclosure mechanical review](https://ohwr.org/project/wr-switch-hw-v4/wikis/enclosure) |
|
|
|
| 08-10-2021 | Presentation at [11th WR Workshop](/project/white-rabbit/wikis/Oct2021Meeting): "Next generation White Rabbit Switch version 4" ([pdf](/project/white-rabbit/wikis/uploads/9b3e06e57f29cc272709055140110ce8/Next_generation_WR_Switch_v4.pdf)) |
|
|
|
| 26-01-2022 | Final and public review of the [WRSv4 Main Board schematics](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics), see [page](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics) |
|
|
|
| 08-04-2022 | Schematics design [v1.0 ready](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics#design-files) |
|
|
|
| 26-01-2022 | Final and public review of the [WRSv4 Main Board schematics](https://ohwr.org/project/wr-switch-hw-v4/-/wikis/WRSv4-v1-Reviews), see [page](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics) |
|
|
|
| 08-04-2022 | Schematics design [v1.0 ready](https://ohwr.org/project/wr-switch-hw-v4/-/wikis/WRSv4-v1-Reviews#design-files) |
|
|
|
| 13-05-2022 | Layout design started. First version expected in 2-3 months.<br>All components ordered, the latest delivery expected in October 2022 |
|
|
|
| 13-02-2023 | First 3 prototypes v1 of the enclosure received (see [Enclosure prototype v1](https://ohwr.org/project/wr-switch-hw-v4/wikis/enclosure-prototype-v1) ) |
|
|
|
| 13-04-2023 | Ordering of components for 30 modules, for upcoming versions. <br>Obsolete/hard-to-source components: HMC6832ALP5LE, IS21ES04G-JCLI,<br>Connector 62674-241121ALF, OSC DOT050V-010.0M, OSC 510FBA125M000AAG |
|
... | ... | |