... | @@ -2,18 +2,12 @@ |
... | @@ -2,18 +2,12 @@ |
|
|
|
|
|
## Project description
|
|
## Project description
|
|
|
|
|
|
This project describes the development of the hardware of the White
|
|
This project describes the development of the hardware of the White Rabbit Switch version 4 (WRS-v4). It is to be release under [CERN-OHL-W v2](https://ohwr.org/project/cernohl/wikis/Documents/CERN-OHL-version-2) license.
|
|
Rabbit Switch version 4 (WRS-v4). It is to be release under [CERN-OHL-W v2](https://ohwr.org/project/cernohl/wikis/Documents/CERN-OHL-version-2) license.
|
|
|
|
|
|
|
|
The White Rabbit Switch is an open hardware design of an **Ethernet switch**. It is a central
|
|
The White Rabbit Switch is an open hardware design of an **Ethernet switch**. It is a central element of a White Rabbit network and is designed as a part of the [White Rabbit project](https://www.ohwr.org/project/white-rabbit/wiki).
|
|
element of a White Rabbit network and is designed as a part of the [White Rabbit
|
|
|
|
project](https://www.ohwr.org/project/white-rabbit/wiki).
|
|
|
|
|
|
|
|
---
|
|
---
|
|
|
|
|
|
|
|
|
|
[![Fig_37_s](uploads/d6017d796b1a4e66468ecd3431fedb1b/Fig_37_s.png)](uploads/f044b9f339cba4d17e62d4f38dce8f45/Fig_37_l_FP.png)
|
|
|
|
|
|
|
|
**Possible design with hot-swappable fans and redundant PSU with basic enclosure**
|
|
**Possible design with hot-swappable fans and redundant PSU with basic enclosure**
|
|
|
|
|
|
## Project information
|
|
## Project information
|
... | @@ -22,7 +16,7 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
... | @@ -22,7 +16,7 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
|
- [Analysis of resource utilization for the candidate FPGA choice](uploads/31c7019f3c24cb12ec0f8c79c108af59/WRS-v4-resource-utilization.pdf) by Creotech - dedicated [project](https://ohwr.org/project/wr-switch-hdl-usp-eval/wikis/home)
|
|
- [Analysis of resource utilization for the candidate FPGA choice](uploads/31c7019f3c24cb12ec0f8c79c108af59/WRS-v4-resource-utilization.pdf) by Creotech - dedicated [project](https://ohwr.org/project/wr-switch-hdl-usp-eval/wikis/home)
|
|
- [WRS-v4 hardare specfications](uploads/094e33be886eeebc0aa8e5e6ff0db06c/WRS-4_Hardware_Specification-v1.1.pdf), based on the following inputs:
|
|
- [WRS-v4 hardare specfications](uploads/094e33be886eeebc0aa8e5e6ff0db06c/WRS-4_Hardware_Specification-v1.1.pdf), based on the following inputs:
|
|
- [Study on the features for the WRS-4](uploads/2309166f9f7deb1249f3fa6fcb99c925/Study_on_the_new_hardware_features_for_the_WRS_4.pdf) by SevenSolutions
|
|
- [Study on the features for the WRS-4](uploads/2309166f9f7deb1249f3fa6fcb99c925/Study_on_the_new_hardware_features_for_the_WRS_4.pdf) by SevenSolutions
|
|
- [WRS-4 main board (Hardware_Architecture)](uploads/c4fa8bc97eeeb551c736146eae7b8e25/WRS-4_main_board_Hardware_Architecture_-v1.7-2020-06-09.pdf) by SevenSolutions
|
|
- [WRS-4 main board (Hardware_Architecture)](uploads/c4fa8bc97eeeb551c736146eae7b8e25/WRS-4_main_board_Hardware_Architecture\_-v1.7-2020-06-09.pdf) by SevenSolutions
|
|
- [WR community feedback and its resolution](https://ohwr.org/project/wr-switch-hw-v4/wikis/Feedback-to-WRS-4-hardware-specification) (to be included in the documents above)
|
|
- [WR community feedback and its resolution](https://ohwr.org/project/wr-switch-hw-v4/wikis/Feedback-to-WRS-4-hardware-specification) (to be included in the documents above)
|
|
- [Connector to expansion board](https://ohwr.org/project/wr-switch-hw-v4/uploads/71655353bc093581e62648502a4cb750/WRS-4_Expansion_Connector.pdf)
|
|
- [Connector to expansion board](https://ohwr.org/project/wr-switch-hw-v4/uploads/71655353bc093581e62648502a4cb750/WRS-4_Expansion_Connector.pdf)
|
|
- [Clocking FMC prototype](https://ohwr.org/project/wr-switch-hw-v4/wikis/Clocking-FMC)
|
|
- [Clocking FMC prototype](https://ohwr.org/project/wr-switch-hw-v4/wikis/Clocking-FMC)
|
... | @@ -33,35 +27,202 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
... | @@ -33,35 +27,202 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
|
- [Frequently Asked Questions](faq)
|
|
- [Frequently Asked Questions](faq)
|
|
- Prototypes
|
|
- Prototypes
|
|
- [v0](https://ohwr.org/project/wr-switch-hw-v4/-/wikis/Prototype-v0)
|
|
- [v0](https://ohwr.org/project/wr-switch-hw-v4/-/wikis/Prototype-v0)
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
---
|
|
---
|
|
|
|
|
|
-----
|
|
|
|
## Project Roadmap
|
|
## Project Roadmap
|
|
|
|
|
|
|**Completion**|**Task**|**Deliverable**|**Status**|
|
|
<table>
|
|
|---------------|--------|---------------|-------|
|
|
<tr>
|
|
|2020: <br /> end March |Study of features, components,<br /> requirements, FPGA/CPU choice - WP1, WP2 | [Study on the features for the WRS-4](uploads/2309166f9f7deb1249f3fa6fcb99c925/Study_on_the_new_hardware_features_for_the_WRS_4.pdf) <br /> [Analysis of FPGA resource utilization](uploads/31c7019f3c24cb12ec0f8c79c108af59/WRS-v4-resource-utilization.pdf) | Completed |
|
|
<th>
|
|
|2020:<br /> end May | 1. Proposal of "WRS-4 main board" - WP3 <br /> 2. Verification of 1Gb transceiver - WP4.1 | 1. Doc:[Proposal of WRS-v4 arch](uploads/c4fa8bc97eeeb551c736146eae7b8e25/WRS-4_main_board_Hardware_Architecture_-v1.7-2020-06-09.pdf)<br /> 2. Demo/prototype | Competed<br />Completed|
|
|
|
|
|2020: <br />June | Request for feedback from WR community | [Request for comments & <br /> WRS-4 Workshop (26 June 2020)](https://forums.ohwr.org/t/new-white-rabbit-switch-4-0-request-for-comments-and-workshop/848506) <br /> [Feedback and its resolution](https://ohwr.org/project/wr-switch-hw-v4/wikis/Feedback-to-WRS-4-hardware-specification) | Completed |
|
|
**Completion**
|
|
|2020: <br />end July | Update of study/proposal documents | Updated documents | Completed |
|
|
</th>
|
|
|2020: <br />end Dec. | 1. Proper WR support for GTH - WP8 <br /> 2. Verification of 10Gb transceiver - WP4.2 |1. Release of WR cores <br /> 2. Demo| |
|
|
<th>
|
|
|2023: <br />end Feb. | 1. Schematics design - WP5 <br /> 2. PCB layout design (DEM) - WP6 <br /> 3. Enclosure design -WP7 | 1 & 2. Prototypes of PCB <br /> 3. Prototype of enclosure | Completed |
|
|
|
|
|tbd | Board Support Package (SW) - WP10 | Prototype | |
|
|
**Task**
|
|
|tbd | Production Test Suite (PTS) - WP9 | Product | |
|
|
</th>
|
|
|2024: <br />end Jun. | 1. Porting of gateware + clocking - WP11 <br /> 2. Port of SW with minimal integration of peripherals - WP12 <br /> 3. Integration of new peripherals - WP13| Fully functional WRS at 1GB | |
|
|
<th>
|
|
| 2024:<br /> end Dec| Preparation of first release v1 with 1Gb for timing and data - WP14 | Release | |
|
|
|
|
| 2025:<br /> end Jun | Add support of 10Gb to the WRS for timing (not data)- WP15 | Prototype | |
|
|
**Deliverable**
|
|
| 2026:<br /> end Jun | Add support of 10Gb to the WRS for data (and timing)- WP17 | Prototype | |
|
|
</th>
|
|
| 2026:<br /> end Dec | Preparation of first release v2 with 10 Gb for timing and data- WP18 | Release | |
|
|
<th>
|
|
|
|
|
|
|
|
**Status**
|
|
-----
|
|
</th>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
2020: <br>end March
|
|
|
|
</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
Study of features, components,<br>requirements, FPGA/CPU choice - WP1, WP2
|
|
|
|
</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
[Study on the features for the WRS-4](uploads/2309166f9f7deb1249f3fa6fcb99c925/Study_on_the_new_hardware_features_for_the_WRS_4.pdf) <br>[Analysis of FPGA resource utilization](uploads/31c7019f3c24cb12ec0f8c79c108af59/WRS-v4-resource-utilization.pdf)
|
|
|
|
</td>
|
|
|
|
<td>Completed</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
2020:<br>end May
|
|
|
|
</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
1\. Proposal of "WRS-4 main board" - WP3 <br>2. Verification of 1Gb transceiver - WP4.1
|
|
|
|
</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
1\. Doc:[Proposal of WRS-v4 arch](uploads/c4fa8bc97eeeb551c736146eae7b8e25/WRS-4_main_board_Hardware_Architecture\_-v1.7-2020-06-09.pdf)<br>2. Demo/prototype
|
|
|
|
</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
Competed<br>Completed
|
|
|
|
</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
2020: <br>June
|
|
|
|
</td>
|
|
|
|
<td>Request for feedback from WR community</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
[Request for comments & <br>WRS-4 Workshop (26 June 2020)](https://forums.ohwr.org/t/new-white-rabbit-switch-4-0-request-for-comments-and-workshop/848506) <br>[Feedback and its resolution](https://ohwr.org/project/wr-switch-hw-v4/wikis/Feedback-to-WRS-4-hardware-specification)
|
|
|
|
</td>
|
|
|
|
<td>Completed</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
2020: <br>end July
|
|
|
|
</td>
|
|
|
|
<td>Update of study/proposal documents</td>
|
|
|
|
<td>Updated documents</td>
|
|
|
|
<td>Completed</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
2020: <br>end Dec.
|
|
|
|
</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
1\. Proper WR support for GTH - WP8 <br>2. Verification of 10Gb transceiver - WP4.2
|
|
|
|
</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
1\. Release of WR cores <br>2. Demo
|
|
|
|
</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
GTHE4 supported (tbd: LPDC)
|
|
|
|
|
|
|
|
10Gb - not yet
|
|
|
|
</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
2023: <br>end Feb.
|
|
|
|
</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
1\. Schematics design - WP5 <br>2. PCB layout design (DEM) - WP6 <br>3. Enclosure design -WP7
|
|
|
|
</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
1 & 2. Prototypes of PCB <br>3. Prototype of enclosure
|
|
|
|
</td>
|
|
|
|
<td>Completed</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>end 2024</td>
|
|
|
|
<td>Board Support Package (SW) - WP10</td>
|
|
|
|
<td>Prototype</td>
|
|
|
|
<td>ongoing</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>tbd</td>
|
|
|
|
<td>Production Test Suite (PTS) - WP9</td>
|
|
|
|
<td>Product</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>end 2024</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
1\. Porting of gateware + clocking - WP11 <br>2. Port of SW with minimal integration of peripherals - WP12 <br>3. Integration of new peripherals - WP13
|
|
|
|
</td>
|
|
|
|
<td>Fully functional WRS at 1GB</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
1. Complieted
|
|
|
|
2. completed
|
|
|
|
3. ongoing
|
|
|
|
</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
2024:<br>end Dec
|
|
|
|
</td>
|
|
|
|
<td>Preparation of first release v1 with 1Gb for timing and data - WP14</td>
|
|
|
|
<td>Release</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
2025:<br>end Jun
|
|
|
|
</td>
|
|
|
|
<td>Add support of 10Gb to the WRS for timing (not data)- WP15</td>
|
|
|
|
<td>Prototype</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
2026:<br>end Jun
|
|
|
|
</td>
|
|
|
|
<td>Add support of 10Gb to the WRS for data (and timing)- WP17</td>
|
|
|
|
<td>Prototype</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
</td>
|
|
|
|
</tr>
|
|
|
|
<tr>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
2026:<br>end Dec
|
|
|
|
</td>
|
|
|
|
<td>Preparation of first release v2 with 10 Gb for timing and data- WP18</td>
|
|
|
|
<td>Release</td>
|
|
|
|
<td>
|
|
|
|
|
|
|
|
</td>
|
|
|
|
</tr>
|
|
|
|
</table>
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
## Work Packages
|
|
## Work Packages
|
|
|
|
|
|
| **WP** | **Task** | **Company** | **Status** |
|
|
| **WP** | **Task** | **Company** | **Status** |
|
|
|-------|--------|-----------|-------|
|
|
|--------|----------|-------------|------------|
|
|
|1| Study of WRS-4 features | Seven Solutions | Completed
|
|
| 1 | Study of WRS-4 features | Seven Solutions | Completed |
|
|
| 2 | Analysis of FPGA resource utilization | Creotech | Competed |
|
|
| 2 | Analysis of FPGA resource utilization | Creotech | Competed |
|
|
| 3 | Proposal of WRS-4 main board architecture | Seven Solutions | Competed |
|
|
| 3 | Proposal of WRS-4 main board architecture | Seven Solutions | Competed |
|
|
| 4 | Verification of 1Gb and 10Gb transceiver | CERN | Ongoing |
|
|
| 4 | Verification of 1Gb and 10Gb transceiver | CERN | Ongoing |
|
... | @@ -71,9 +232,9 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
... | @@ -71,9 +232,9 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
|
| 7 | Enclosure design | Seven Solutions | Competed |
|
|
| 7 | Enclosure design | Seven Solutions | Competed |
|
|
| 8 | Proper WR support for GTH | CERN | |
|
|
| 8 | Proper WR support for GTH | CERN | |
|
|
| 9 | Production Test Suite (PTS) | | |
|
|
| 9 | Production Test Suite (PTS) | | |
|
|
|10| Board Support Package (SW) | | |
|
|
| 10 | Board Support Package (SW) | CERN/GMV | |
|
|
| 11 | Porting of gateware + clocking | | |
|
|
| 11 | Porting of gateware + clocking | | |
|
|
|12| OS/bootloader support and port of SW <br /> with minimal integration of peripherals | | |
|
|
| 12 | OS/bootloader support and port of SW <br>with minimal integration of peripherals | | |
|
|
| 13 | Integration of new peripherals | | |
|
|
| 13 | Integration of new peripherals | | |
|
|
| 14 | Preparation of first release v1 | CERN | |
|
|
| 14 | Preparation of first release v1 | CERN | |
|
|
| 15 | Add support of 10Gb to the WRS (timing, not data | | |
|
|
| 15 | Add support of 10Gb to the WRS (timing, not data | | |
|
... | @@ -81,9 +242,8 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
... | @@ -81,9 +242,8 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
|
| 17 | Add support of 10Gb for data | M2TECH | |
|
|
| 17 | Add support of 10Gb for data | M2TECH | |
|
|
| 18 | Preparation of first release v2 | CERN | |
|
|
| 18 | Preparation of first release v2 | CERN | |
|
|
| 19 | Preparation of testbed for the WRS-4 | | |
|
|
| 19 | Preparation of testbed for the WRS-4 | | |
|
|
-----
|
|
|
|
|
|
|
|
|
|
|
|
|
|
---
|
|
|
|
|
|
## Contacts
|
|
## Contacts
|
|
|
|
|
... | @@ -92,22 +252,21 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
... | @@ -92,22 +252,21 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
|
- [Seven Solutions](https://sevensols.com/)
|
|
- [Seven Solutions](https://sevensols.com/)
|
|
- [Creotech](https://creotech.pl/pl/home-3-3-3-2/)
|
|
- [Creotech](https://creotech.pl/pl/home-3-3-3-2/)
|
|
|
|
|
|
|
|
|
|
### General question about project
|
|
### General question about project
|
|
|
|
|
|
- [Maciej Lipinski](mailto:maciej.lipinski@cern.ch) - CERN
|
|
- [Maciej Lipinski](mailto:maciej.lipinski@cern.ch) - CERN
|
|
|
|
|
|
-----
|
|
---
|
|
|
|
|
|
## Status
|
|
## Status
|
|
|
|
|
|
| **Date** | **Event** |
|
|
| **Date** | **Event** |
|
|
|----|----|
|
|
|----------|-----------|
|
|
| 07-03-2014 | First ideas of a next generation WRS with one or more 10 Gbps ports |
|
|
| 07-03-2014 | First ideas of a next generation WRS with one or more 10 Gbps ports |
|
|
| 01-07-2016 | First collection of requirements for V4 generation switch requested on [wr-dev mailing list](https://lists.ohwr.org/sympa/arc/white-rabbit-dev/2016-07/thrd1.html#00000) (archive) |
|
|
| 01-07-2016 | First collection of requirements for V4 generation switch requested on [wr-dev mailing list](https://lists.ohwr.org/sympa/arc/white-rabbit-dev/2016-07/thrd1.html#00000) (archive) |
|
|
| 07-10-2018 | Second collection of requirements for V4 generation switch made on the [10th WR Workshop](https://www.ohwr.org/project/white-rabbit/wikis/oct2018meeting) |
|
|
| 07-10-2018 | Second collection of requirements for V4 generation switch made on the [10th WR Workshop](https://www.ohwr.org/project/white-rabbit/wikis/oct2018meeting) |
|
|
| 30-09-2018 | First "Technical proposal for the design of a new White Rabbit Switch" by [Seven Solutions](https://sevensols.com/) |
|
|
| 30-09-2018 | First "Technical proposal for the design of a new White Rabbit Switch" by [Seven Solutions](https://sevensols.com/) |
|
|
|28-11-2018 | [Seven Solutions](https://sevensols.com/) ordered to conduct preliminary design study and produce Technical <br />Specification with definition of architecture and key components selection)|
|
|
| 28-11-2018 | [Seven Solutions](https://sevensols.com/) ordered to conduct preliminary design study and produce Technical <br>Specification with definition of architecture and key components selection) |
|
|
| 11-07-2019 | Candidate FPGAs: Xilinx Zynq Ultrascale+ and Intel Arria 10 |
|
|
| 11-07-2019 | Candidate FPGAs: Xilinx Zynq Ultrascale+ and Intel Arria 10 |
|
|
| 31-07-2019 | [Creotech](https://creotech.pl/pl/home-3-3-3-2/) ordered to perform evaluation of the required resources |
|
|
| 31-07-2019 | [Creotech](https://creotech.pl/pl/home-3-3-3-2/) ordered to perform evaluation of the required resources |
|
|
| 31-07-2019 | Meeting with CERN IT experts (see [notes](https://ohwr.org/project/wr-switch-hw-v4/wikis/features-choice-meeting-with-it)) |
|
|
| 31-07-2019 | Meeting with CERN IT experts (see [notes](https://ohwr.org/project/wr-switch-hw-v4/wikis/features-choice-meeting-with-it)) |
|
... | @@ -116,27 +275,20 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
... | @@ -116,27 +275,20 @@ project](https://www.ohwr.org/project/white-rabbit/wiki). |
|
| 28-02-2020 | Final choice of FPGA: Zynq Ultrascale+ XCZU17EG-1FFVC1760E |
|
|
| 28-02-2020 | Final choice of FPGA: Zynq Ultrascale+ XCZU17EG-1FFVC1760E |
|
|
| 01-04-2020 | [Seven Solutions](https://sevensols.com/) delivered final version of [Study on the features for the WRS-4](uploads/2309166f9f7deb1249f3fa6fcb99c925/Study_on_the_new_hardware_features_for_the_WRS_4.pdf) |
|
|
| 01-04-2020 | [Seven Solutions](https://sevensols.com/) delivered final version of [Study on the features for the WRS-4](uploads/2309166f9f7deb1249f3fa6fcb99c925/Study_on_the_new_hardware_features_for_the_WRS_4.pdf) |
|
|
| 04-06-2020 | Start of WP5.1 (Clocking FMC design) |
|
|
| 04-06-2020 | Start of WP5.1 (Clocking FMC design) |
|
|
|09-06-2020 | [Seven Solutions](https://sevensols.com/) delivered final version of [WRS-4 main board (Hardware_Architecture)](uploads/c4fa8bc97eeeb551c736146eae7b8e25/WRS-4_main_board_Hardware_Architecture_-v1.7-2020-06-09.pdf)|
|
|
| 09-06-2020 | [Seven Solutions](https://sevensols.com/) delivered final version of [WRS-4 main board (Hardware_Architecture)](uploads/c4fa8bc97eeeb551c736146eae7b8e25/WRS-4_main_board_Hardware_Architecture\_-v1.7-2020-06-09.pdf) |
|
|
| 26-06-2020 | [New WRS-4 Workshop](https://www.ohwr.org/project/white-rabbit/wikis/New-WRS-4-Workshop) |
|
|
| 26-06-2020 | [New WRS-4 Workshop](https://www.ohwr.org/project/white-rabbit/wikis/New-WRS-4-Workshop) |
|
|
| 18-09-2020 | [Clocking FMC schematics review](https://ohwr.org/project/wr-switch-hw-v4/wikis/Clocking-FMC) |
|
|
| 18-09-2020 | [Clocking FMC schematics review](https://ohwr.org/project/wr-switch-hw-v4/wikis/Clocking-FMC) |
|
|
| 16-11-2020 | [WR community feedback and its resolution](https://ohwr.org/project/wr-switch-hw-v4/wikis/Feedback-to-WRS-4-hardware-specification) |
|
|
| 16-11-2020 | [WR community feedback and its resolution](https://ohwr.org/project/wr-switch-hw-v4/wikis/Feedback-to-WRS-4-hardware-specification) |
|
|
| 19-11-2020 | [WRS-4 Hardware Specification](uploads/f6243e1cf7bc4fcde92e8e818fe461eb/WRS-4_Hardware_Specification-v1.1.pdf) published. It is based on previous feedback and used for the first prototype |
|
|
| 19-11-2020 | [WRS-4 Hardware Specification](uploads/f6243e1cf7bc4fcde92e8e818fe461eb/WRS-4_Hardware_Specification-v1.1.pdf) published. It is based on previous feedback and used for the first prototype |
|
|
|01-02-2021| [Main board schematics review](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics)
|
|
| 01-02-2021 | [Main board schematics review](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics) |
|
|
| 11-02-2021 | [Clocking FMC](https://ohwr.org/project/wr-switch-hw-v4/wikis/Clocking-FMC) delivered to CERN |
|
|
| 11-02-2021 | [Clocking FMC](https://ohwr.org/project/wr-switch-hw-v4/wikis/Clocking-FMC) delivered to CERN |
|
|
| 11-04-2021 | [Enclosure mechanical review](https://ohwr.org/project/wr-switch-hw-v4/wikis/enclosure) |
|
|
| 11-04-2021 | [Enclosure mechanical review](https://ohwr.org/project/wr-switch-hw-v4/wikis/enclosure) |
|
|
| 08-10-2021 | Presentation at [11th WR Workshop](/project/white-rabbit/wikis/Oct2021Meeting): "Next generation White Rabbit Switch version 4" ([pdf](/project/white-rabbit/wikis/uploads/9b3e06e57f29cc272709055140110ce8/Next_generation_WR_Switch_v4.pdf)) |
|
|
| 08-10-2021 | Presentation at [11th WR Workshop](/project/white-rabbit/wikis/Oct2021Meeting): "Next generation White Rabbit Switch version 4" ([pdf](/project/white-rabbit/wikis/uploads/9b3e06e57f29cc272709055140110ce8/Next_generation_WR_Switch_v4.pdf)) |
|
|
| 26-01-2022 | Final and public review of the [WRSv4 Main Board schematics](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics), see [page](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics) |
|
|
| 26-01-2022 | Final and public review of the [WRSv4 Main Board schematics](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics), see [page](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics) |
|
|
| 08-04-2022 | Schematics design [v1.0 ready](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics#design-files) |
|
|
| 08-04-2022 | Schematics design [v1.0 ready](https://ohwr.org/project/wr-switch-hw-v4/wikis/wrs-v4-main-board-schematics#design-files) |
|
|
|13-05-2022| Layout design started. First version expected in 2-3 months.<br/>All components ordered, the latest delivery expected in October 2022 |
|
|
| 13-05-2022 | Layout design started. First version expected in 2-3 months.<br>All components ordered, the latest delivery expected in October 2022 |
|
|
| 13-02-2023 | First 3 prototypes v1 of the enclosure received (see [Enclosure prototype v1](https://ohwr.org/project/wr-switch-hw-v4/wikis/enclosure-prototype-v1) ) |
|
|
| 13-02-2023 | First 3 prototypes v1 of the enclosure received (see [Enclosure prototype v1](https://ohwr.org/project/wr-switch-hw-v4/wikis/enclosure-prototype-v1) ) |
|
|
|13-04-2023| Ordering of components for 30 modules, for upcoming versions. <br> Obsolete/hard-to-source components: HMC6832ALP5LE, IS21ES04G-JCLI,<br/>Connector 62674-241121ALF, OSC DOT050V-010.0M, OSC 510FBA125M000AAG |
|
|
| 13-04-2023 | Ordering of components for 30 modules, for upcoming versions. <br>Obsolete/hard-to-source components: HMC6832ALP5LE, IS21ES04G-JCLI,<br>Connector 62674-241121ALF, OSC DOT050V-010.0M, OSC 510FBA125M000AAG |
|
|
| 16-05-2023 | [Layout review 20230516](https://ohwr.org/project/wr-switch-hw-v4/wikis/layout-review-20230516) |
|
|
| 16-05-2023 | [Layout review 20230516](https://ohwr.org/project/wr-switch-hw-v4/wikis/layout-review-20230516) |
|
|
| 12-12-2023 | [Layout finalisations and SI/PI 20231212](https://ohwr.org/project/wr-switch-hw-v4/wikis/layout-finalisations-and-si,pi-20231212) |
|
|
| 12-12-2023 | [Layout finalisations and SI/PI 20231212](https://ohwr.org/project/wr-switch-hw-v4/wikis/layout-finalisations-and-si,pi-20231212) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|