# Complete status
|
|
|
|
|
|
|
|
## Status
|
|
|
|
|
|
|
|
<table>
|
|
|
|
<tbody>
|
|
|
|
<tr class="odd">
|
|
|
|
<td><strong>Date</strong></td>
|
|
|
|
<td><b> Event </b></td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>22-06-2010</td>
|
|
|
|
<td>Start of project. Design will be done by an external company, based on the <a href="https://www.ohwr.org/project/fmc-pci-carrier">FMC PCIe Carrier</a>.<br />
|
|
|
|
Reviewing will be done by CERN.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>29-06-2010</td>
|
|
|
|
<td>Main features reviewed by JS, PA, MC & EB. Design can start.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>12-07-2010</td>
|
|
|
|
<td>First schematics published. Ready for review.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>16-07-2010</td>
|
|
|
|
<td>First review held. Considered as a preliminary review as schematics not finished.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>24-07-2010</td>
|
|
|
|
<td>Second version schematics published.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>03-08-2010</td>
|
|
|
|
<td>Second schematics review held. FMC to Xilinx bank connections not correct.<br />
|
|
|
|
Clock missing. Supply Xilinx wrong. Cleanup required.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>03-09-2010</td>
|
|
|
|
<td>Schematics corrected. Waiting for a final schematics review from CERN.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>07-09-2010</td>
|
|
|
|
<td>Third schematics review held. [review07092010](review07092010)</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>10-09-2010</td>
|
|
|
|
<td>Review comments integrated <a href="review07092010comments" class="uri">review07092010comments</a>. Start of PCB layout.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>21-09-2010</td>
|
|
|
|
<td>PCB layout being made. Will fit on a 6-layer board.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>27-09-2010</td>
|
|
|
|
<td>PCB layout 'ready'.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>01-10-2010</td>
|
|
|
|
<td>PCB layout modified before review.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>04-10-2010</td>
|
|
|
|
<td>Preliminary PCB layout review requiring modifications to layout. [review04102010](review04102010)</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>05-10-2010</td>
|
|
|
|
<td>PCB layout review held. [review05102010](review05102010)</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>08-10-2010</td>
|
|
|
|
<td><a href="https://edh.cern.ch/Document/SupplyChain/DAI/4476636">Order</a> placed for production of three prototypes.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>18-10-2010</td>
|
|
|
|
<td>Some final mods to the schematics and PCB. Design passses CERN's design office for standard production files.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>19-10-2010</td>
|
|
|
|
<td>Board could not generate interrupts. Found before finalising production files.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>20-10-2010</td>
|
|
|
|
<td>Vias designed next to BGA pads which may cause production problems. Needs rework of layout.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>29-10-2010</td>
|
|
|
|
<td>Received improved layout. Will pass via CERN's design office.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>05-11-2010</td>
|
|
|
|
<td>Design finished. Expect ordered boards by <del>mid December</del> January.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>20-12-2010</td>
|
|
|
|
<td>Production of 3 prototype board finished (see photo above)</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>19-01-2011</td>
|
|
|
|
<td>Three prototypes arrived at CERN.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>19-01-2011</td>
|
|
|
|
<td>Started testing V1 [TestingV1](TestingV1)</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>04-02-2011</td>
|
|
|
|
<td>First DDR3 access</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>04-02-2011</td>
|
|
|
|
<td>WhiteRabbit port GTP transceiver working. Packet Tx/Rx in progress...</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>06-02-2011</td>
|
|
|
|
<td>Packet transmission and reception works!</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>24-02-2011</td>
|
|
|
|
<td>All ICs and most slow lines of FMC connector tested. Not yet gigabit lines.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>02-03-2011</td>
|
|
|
|
<td>Review of "V1.1" schematics and PCB.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>07-03-2011</td>
|
|
|
|
<td>Ordered 10 "V1.1" boards for CERN. Company will produce extra for <a href="https://www.ohwr.org/project/white-rabbit">WR</a> development.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>11-04-2011</td>
|
|
|
|
<td>Improved version of "V1.1" layout sent for verification by CERN's design office. Planned ready by 29-04-2011.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>18-04-2011</td>
|
|
|
|
<td>First V1.1 prototypes received, start testing them.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>02-05-2011</td>
|
|
|
|
<td>V1.1 partly tested. Cleaning up schematics for production. Found missing pull-ups.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>09-05-2011</td>
|
|
|
|
<td>Review of updated schematics planned to be held on 11-05-2011. [review11052011](review11052011)</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>16-05-2011</td>
|
|
|
|
<td>Schematics, layout and production documents for V2 are available in [EDMS](https://edms.cern.ch/nav/P:EDA-02189:V0/I:EDA-02189-V2-0:V0/TAB4)</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>20-05-2011</td>
|
|
|
|
<td>CERN sent out price enquiry for production of 70 boards. Delivery of pre-series in October.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>31-05-2011</td>
|
|
|
|
<td>Sent order for 3 production prototypes. <a href="http://edh.cern.ch/Info/Order/CA/1519947">Order</a> (CERN only).<br />
|
|
|
|
Demo of production test software shown. Needs only minor modifications.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>16-06-2011</td>
|
|
|
|
<td>V2 boards being built.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>01-07-2011</td>
|
|
|
|
<td>Three V2 boards received. One fully tested OK. Two only shortly tested.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>14-07-2011</td>
|
|
|
|
<td>Modifications for V3 (OHL v1.1, 1 crossover SATA), [changelog](V3ChangeLog)</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>17-07-2011</td>
|
|
|
|
<td>Order placed for 70 SPEC cards at Seven Solutions. First batch expected end October.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>25-07-2011</td>
|
|
|
|
<td>V3 released. But never built.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>23-08-2011</td>
|
|
|
|
<td>V4 released. Solves a minor mechanical problem with the SFP connector.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>21-11-2011</td>
|
|
|
|
<td>Pre-production serie of 10 boards was not compliant to IPC-A-610 (Class 2).</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>16-01-2012</td>
|
|
|
|
<td>Will receive <del>8</del> 11 boards by <del>mid February</del> 7 March. (Update 24-02-2012), another 59 by end April.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>14-03-2012</td>
|
|
|
|
<td>CERN accepted the 10 preseries boards that were received on 7 March.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>26-04-2012</td>
|
|
|
|
<td>Will receive another 27 cards from Seven Solution by mid-June. And 33 out of the order of 70 later.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>12-06-2012</td>
|
|
|
|
<td>SPEC boards passed most restrictive EMC tests for industrial and domestic classes. [Test report](https://www.ohwr.org/project/spec/wikis/Documents/EMC-Test-report).</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>13-06-2012</td>
|
|
|
|
<td>CERN ordered 60 cards at INCAA for delivery end September.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>03-07-2012</td>
|
|
|
|
<td>Seven Solutions delivered 52 cards. 8 to be delivered later.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="odd">
|
|
|
|
<td>18-07-2012</td>
|
|
|
|
<td>Seven Solutions delivered final 8 cards.</td>
|
|
|
|
</tr>
|
|
|
|
<tr class="even">
|
|
|
|
<td>10-09-2012</td>
|
|
|
|
<td>CERN entered the modules in the stock for later use in LHC and other accelerators.</td>
|
|
|
|
</tr>
|
|
|
|
</tbody>
|
|
|
|
</table>
|
|
|
|
|
|
|
|
-----
|
|
|
|
|
|
|
|
Erik van der Bij - 5 November 2012
|
|
|
|
|