... | ... | @@ -297,6 +297,10 @@ production of 50 series (original foreseen for delivery in May 2013) started</td |
|
|
<td>Added White Rabbit support for SVEC and SPEC</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>04-07-2014</td>
|
|
|
<td>Ordered 60 V3-1 boards: 20 for delivery by end October 2014, 40 by begin January 2015 ([check order](https://edh.cern.ch/Document/SupplyChain/DAI/5718677))</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>10-07-2014</td>
|
|
|
<td>Project split into hw, gw, sw sub-projects</td>
|
|
|
</tr>
|
... | ... | @@ -305,5 +309,5 @@ production of 50 series (original foreseen for delivery in May 2013) started</td |
|
|
|
|
|
-----
|
|
|
|
|
|
Eva Gousiou | Javier Serrano | Erik van der Bij | 3 July 2014
|
|
|
Eva Gousiou | Javier Serrano | Erik van der Bij | 22 July 2014
|
|
|
|