<td>06-12-2010</td>
|
|
|
<td>Project start.</td>
|
|
|
<td>Project start</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>14-12-2010</td>
|
|
|
<td>First specification available for comments.</td>
|
|
|
<td>First specification available for comments</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>09-03-2011</td>
|
... | ... | @@ -192,47 +192,47 @@ sub-project has its corresponding release. |
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>18-03-2011</td>
|
|
|
<td>Second schematics design review held.</td>
|
|
|
<td>Second schematics design review held</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>08-04-2011</td>
|
|
|
<td>First layout made. Review made, needs moving of components [Review08042011](Review08042011).</td>
|
|
|
<td>First layout made. Review made, needs moving of components ([check review#1](https://www.ohwr.org/documents/338))</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>11-04-2011</td>
|
|
|
<td>Layout being modified. Planning: 3 assembled prototypes by 16 May.</td>
|
|
|
<td>Layout being modified. Planning: 3 assembled prototypes by 16 May</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>19-04-2011</td>
|
|
|
<td>New layout received. Design review on 20-04-2011.</td>
|
|
|
<td>New layout received. Design review on 20-04-2011</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>20-04-2011</td>
|
|
|
<td>Review held <a href="Review20042011" class="uri">Review20042011</a>. Layout office modifies the design.</td>
|
|
|
<td>Review held (<a href="https://www.ohwr.org/documents/338">check review#2</a> ); layout office modifies the design</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>29-04-2011</td>
|
|
|
<td>Layout office finalised the design.</td>
|
|
|
<td>Layout office finalized the design</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>30-05-2011</td>
|
|
|
<td>Three prototypes ready.</td>
|
|
|
<td>Three prototypes ready</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>01-06-2011</td>
|
|
|
<td>Start of writing firmware.</td>
|
|
|
<td>Start of writing firmware</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>05-08-2011</td>
|
|
|
<td>Design specification review held. [https://www.ohwr.org/documents/91](https://www.ohwr.org/project/https/wikis)</td>
|
|
|
<td>Design specification review held (<a href="https://www.ohwr.org/project/fmc-tdc-1ns-5cha-gw/tree/fea36da15faebc79c4de4406472e80506b880969/hdl/spec/src/code_review_08-11-2011">check review</a> )</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>08-08-2011</td>
|
|
|
<td>Basic functionality OK. Several issues found that need a new PCB layout.</td>
|
|
|
<td>Basic functionality OK. Several issues found that need a new PCB layout</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>16-12-2011</td>
|
|
|
<td>New PCB layout made. Production files will be generated.</td>
|
|
|
<td>New PCB layout made. Production files will be generated</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>02-02-2012</td>
|
... | ... | @@ -240,60 +240,64 @@ sub-project has its corresponding release. |
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>07-02-2012</td>
|
|
|
<td>Schematics reviewed: (<a href="review07022012)">review07022012</a>. Improved schematics ready by 21-02-2012 for new review.</td>
|
|
|
<td>Schematics reviewed (<a href="https://www.ohwr.org/documents/338">check review#3</a> ); improved schematics ready by 21-02-2012 for new review</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>30-05-2012</td>
|
|
|
<td>V2 boards received.</td>
|
|
|
<td>V2 boards received</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>30-08-2012</td>
|
|
|
<td>V3 schematics and PCB being made. Input circuit modified.</td>
|
|
|
<td>V3 schematics and PCB being made; input circuit modified</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>23-10-2012</td>
|
|
|
<td>V3 schematics and PCB ready.</td>
|
|
|
<td>V3 schematics and PCB ready</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>15-11-2012</td>
|
|
|
<td>Ordered 60 V3 boards (10 for delivery by <del>begin March</del> end April 2013, 50 by begin May 2013). ([order](https://edh.cern.ch/Document/SupplyChain/DAI/5108860))</td>
|
|
|
<td>Ordered 60 V3 boards: 10 for delivery by <del>begin March</del> end April 2013, 50 by begin May 2013 ([check order](https://edh.cern.ch/Document/SupplyChain/DAI/5108860))</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>04-12-2012</td>
|
|
|
<td>Feedback on design received. Can use same PCB. Other changes may be handled in a V4.</td>
|
|
|
<td>Feedback on design received. Can use same PCB. Other changes may be handled in a V4</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>25-03-2013</td>
|
|
|
<td>Will make V3-1 design (only change of BOM) to handle [five issues](https://www.ohwr.org/project/fmc-tdc/versions/15).</td>
|
|
|
<td>Will make V3-1 design (only change of BOM) to handle [five issues](https://www.ohwr.org/project/fmc-tdc/versions/15)</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>08-04-2013</td>
|
|
|
<td>Working on: correcting two firmware bugs, writing documentation, writing software to test firmware.</td>
|
|
|
<td>Working on: correcting two firmware bugs, writing documentation, writing software to test firmware</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>26-04-2013</td>
|
|
|
<td>No known firmware bugs left. Writing calibration test program.</td>
|
|
|
<td>No known firmware bugs left. Writing calibration test program</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>06-05-2013</td>
|
|
|
<td>V3-1 design ready (only change of BOM) to handle [five issues](https://www.ohwr.org/project/fmc-tdc/versions/15).</td>
|
|
|
<td>V3-1 design ready (only change of BOM) to handle [five issues](https://www.ohwr.org/project/fmc-tdc/versions/15)</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>13-05-2013</td>
|
|
|
<td>CERN received 9 pre-series V3-1 boards.</td>
|
|
|
<td>CERN received 9 pre-series V3-1 boards</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>22-05-2013</td>
|
|
|
<td>CERN accepted quality of pre-series V3-1 boards.<br />
|
|
|
Production of 50 series (original foreseen for delivery in May 2013) started.</td>
|
|
|
<td>CERN accepted quality of pre-series V3-1 boards;<br />
|
|
|
production of 50 series (original foreseen for delivery in May 2013) started</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>09-08-2013</td>
|
|
|
<td>51 V3-1 boards received.</td>
|
|
|
<td>51 V3-1 boards received</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>20-06-2014</td>
|
|
|
<td>Added White Rabbit support for SVEC and SPEC.</td>
|
|
|
<td>Added White Rabbit support for SVEC and SPEC</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>10-07-2014</td>
|
|
|
<td>Project split into hw, gw, sw sub-projects</td>
|
|
|
</tr>
|
|
|