## PCB versions
|
|
|
### Working versions
|
|
|
* EDA-03287-V5 studies launched end 2021, to solve below problems and in addition cope with electronics components shortage
|
|
|
* [EDA-03287-V5](https://edms.cern.ch/item/EDA-03287-V5-0/)
|
|
|
* studies launched end 2021, to solve below problems and in addition cope with electronics components shortage - see also CERN internal https://gitlab.cern.ch/abt-projects/electronics/eda-03287-v5/-/blob/master/readme.md#changes-wrt-v4)
|
|
|
* produced and tested Q2 2022, all good
|
|
|
* [EDA-03287-V4](https://edms.cern.ch/item/EDA-03287-V4-0/)
|
|
|
* Modifications required for proper operation:
|
|
|
* To get rid of the N12V0 100mV ripple, place the not-mounted C1 capacitor of 150pF. This will render the LM2611 (IC2) feedback loop stable.
|
... | ... | @@ -158,8 +160,9 @@ An automated test procedure exists, see https://wikis.cern.ch/display/TEABT/FMC+ |
|
|
|20-01-2017|designer Simon has left CERN, Pieter taking over|
|
|
|
|10-08-2017|Production launch of pre-series: 12x FMC V3|
|
|
|
|10-10-2017|Pre-series arrived, tests ongoing - so far so good|
|
|
|
|2019|Produced series of 50x V4|
|
|
|
|17-12-2021|CERN BE-OP needs 26 cards (+6 for ABT), launch V5 design with small corrections|
|
|
|
|2019|Production of 50x V4 done|
|
|
|
|17-12-2021|CERN BE-OP needs 24 cards (+6 for ABT), launch V5 design with small corrections|
|
|
|
|17-06-2022|Production of 30x V5 done|
|
|
|
|
|
|
|
|
|
|
... | ... | |