## Project Status
|
|
|
|
|
|
<table>
|
|
|
<tbody>
|
|
|
<tr class="odd">
|
|
|
<td><strong>Date</strong></td>
|
|
|
<td><b> Event </b></td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>02-06-2015</td>
|
|
|
<td>First ideas for the I/O card.</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>27-07-2015</td>
|
|
|
<td>Creation of Open Hardware project, selection of connector and fast comparator.</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>04-09-2015</td>
|
|
|
<td>Design specification: Bandwidth, I/O levels, DAC choice</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>08-09-2015</td>
|
|
|
<td>First schematics and reviewing process</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>02-11-2015</td>
|
|
|
<td><a href="https://www.ohwr.org/project/fmc-dio-10i-8o/wikis/Documents/Schematics-first-draft">Schematics, first draft</a> available</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>06-11-2015</td>
|
|
|
<td><a href="/Review-first-draft">Review with BE-CO team</a> and its [corrections](/Corrections-after-Review-first-draw)</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>24-11-2015</td>
|
|
|
<td><a href="https://www.ohwr.org/project/fmc-dio-10i-8o/wikis/Documents/Schematics-second-draft">Schematics, second draft</a> available</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>26-11-2015</td>
|
|
|
<td>Review of the PCB-layout from BE/CO department</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>02-12-2015</td>
|
|
|
<td>Schematics sent to CERN design office for PCB layout</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>28-01-2016</td>
|
|
|
<td><a href="https://www.ohwr.org/project/fmc-dio-10i-8o/wikis/Documents/FMC-V1">FMC V1</a> in production</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>25-02-2016</td>
|
|
|
<td><a href="/Breakout-board">Breakout board</a> created</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>21-03-2016</td>
|
|
|
<td>VDHL code writing process started</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>27-04-2016</td>
|
|
|
<td>Reception of two FMC V1 prototypes, beginning of hardware and software tests</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>25-07-2016</td>
|
|
|
<td>Patch panel sent to production</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>01-09-2016</td>
|
|
|
<td>FMC V2 required because problems with LMH7324 availability and incorrect power supply components</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>16-09-2016</td>
|
|
|
<td>FMC V2 with new schematics and new layout</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>20-10-2016</td>
|
|
|
<td>Production of 6x FMC V2 samples</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>20-01-2017</td>
|
|
|
<td>designer Simon has left CERN, Pieter taking over</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>10-08-2017</td>
|
|
|
<td>Production launch of pre-series: 12x FMC V3</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>10-10-2017</td>
|
|
|
<td>Pre-series arrived, tests ongoing - so far so good</td>
|
|
|
</tr>
|
|
|
</tbody>
|
|
|
</table>
|
|
|
|**Date**|**Event**|
|
|
|
|----|----|
|
|
|
|02-06-2015|First ideas for the I/O card.|
|
|
|
|27-07-2015|Creation of Open Hardware project, selection of connector and fast comparator.|
|
|
|
|04-09-2015|Design specification: Bandwidth, I/O levels, DAC choice|
|
|
|
|08-09-2015|First schematics and reviewing process|
|
|
|
|02-11-2015|[Schematics, first draft](https://www.ohwr.org/project/fmc-dio-10i-8o/wikis/Documents/Schematics-first-draft) available|
|
|
|
|06-11-2015|[Review with BE-CO team](/Review-first-draft) and its [corrections](/Corrections-after-Review-first-draw)|
|
|
|
|24-11-2015|[Schematics, second draft](https://www.ohwr.org/project/fmc-dio-10i-8o/wikis/Documents/Schematics-second-draft) available|
|
|
|
|26-11-2015|Review of the PCB-layout from BE/CO department|
|
|
|
|02-12-2015|Schematics sent to CERN design office for PCB layout|
|
|
|
|28-01-2016|[FMC V1](https://www.ohwr.org/project/fmc-dio-10i-8o/wikis/Documents/FMC-V1) in production|
|
|
|
|25-02-2016|[Breakout board](/Breakout-board) created|
|
|
|
|21-03-2016|VDHL code writing process started|
|
|
|
|27-04-2016|Reception of two FMC V1 prototypes, beginning of hardware and software tests|
|
|
|
|25-07-2016|Patch panel sent to production|
|
|
|
|01-09-2016|FMC V2 required because problems with LMH7324 availability and incorrect power supply components|
|
|
|
|16-09-2016|FMC V2 with new schematics and new layout|
|
|
|
|20-10-2016|Production of 6x FMC V2 samples|
|
|
|
|20-01-2017|designer Simon has left CERN, Pieter taking over|
|
|
|
|10-08-2017|Production launch of pre-series: 12x FMC V3|
|
|
|
|10-10-2017|Pre-series arrived, tests ongoing - so far so good|
|
|
|
|
|
|
|
|
|
-----
|
|
|
|
|
|
21 October 2016
|
|
|
|
|
|
|