## Project Status
|
|
|
|
|
|
<table>
|
|
|
<tbody>
|
|
|
<tr class="odd">
|
|
|
<td><strong>Date</strong></td>
|
|
|
<td><b> Event </b></td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>04-01-2016</td>
|
|
|
<td>Work on schematics started.</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>27-01-2016</td>
|
|
|
<td>First version of schematics ready for review.</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>05-02-2016</td>
|
|
|
<td>Layout started by CERN design office.</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>08-02-2016</td>
|
|
|
<td>Inclusion of project on OHWR.</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>15-03-2016</td>
|
|
|
<td>Layout completed.</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>27-05-2016</td>
|
|
|
<td>First two prototype boards received.</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>10-08-2016</td>
|
|
|
<td>First prototype boards under test.</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>12-08-2016</td>
|
|
|
<td>Some small <a href="https://www.ohwr.org/project/fmc-del-1ns-2cha/versions/135">issues</a> found but the board is functional.</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>03-11-2016</td>
|
|
|
<td>First two prototype boards deployed (on a SVEC) in LHC for control of Schottky Monitor fast gates.</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>19-01-2017</td>
|
|
|
<td>Module presented at the BI Technical Board ([slides](https://indico.cern.ch/event/587494/contributions/2367714/1394441)).</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>01-05-2017</td>
|
|
|
<td>Decision to change from surface mount SMA connectors to through hole due to reliability issues.<br />
|
|
|
<a href="http://www.amphenolrf.com/901-10138.html">Amphenol 901-10138</a> selected as a replacement.</td>
|
|
|
</tr>
|
|
|
</tbody>
|
|
|
</table>
|
|
|
|
|
|
-----
|
|
|
| **Date**| \* Event \*|
|
|
|
| 04-01-2016 | Work on schematics started. |
|
|
|
| 27-01-2016 | First version of schematics ready for review. |
|
|
|
| 05-02-2016 | Layout started by CERN design office. |
|
|
|
| 08-02-2016 | Inclusion of project on OHWR. |
|
|
|
| 15-03-2016 | Layout completed. |
|
|
|
| 27-05-2016 | First two prototype boards received. |
|
|
|
| 10-08-2016 | First prototype boards under test. |
|
|
|
| 12-08-2016 | Some small
|
|
|
[issues](https://www.ohwr.org/project/fmc-del-1ns-2cha/versions/135)
|
|
|
found but the board is functional. |
|
|
|
| 03-11-2016 | First two prototype boards deployed (on a SVEC) in LHC
|
|
|
for control of Schottky Monitor fast gates. |
|
|
|
| 19-01-2017 | Module presented at the BI Technical Board
|
|
|
([slides](https://indico.cern.ch/event/587494/contributions/2367714/1394441)).
|
|
|
|
|
|
|
| 01-05-2017 | Decision to change from surface mount SMA connectors to
|
|
|
through hole due to reliability issues.
|
|
|
[Amphenol 901-10138](http://www.amphenolrf.com/901-10138.html) selected
|
|
|
as a replacement. |
|
|
|
| 22-05-2017 | Version 3 design changes finished. |
|
|
|
\---
|
|
|
|
|
|
Michael Betz, Tom Levens - 09 February 2016
|
|
|
|