... | ... | @@ -12,35 +12,42 @@ |
|
|
- Corresponding [Delivery schedule Gantt
|
|
|
chart](/Planning#task-planning)
|
|
|
|
|
|
<!-- end list -->
|
|
|
|
|
|
- \_This technical specification concerns the supply of 100 assembled
|
|
|
and tested ACME\_1 printed circuit boards, also known as EDA-02063
|
|
|
boards.
|
|
|
The delivery of the pre-series of 20 boards is required to be within
|
|
|
15 weeks following placement of the contract, while the remaining 80
|
|
|
boards are required to be delivered within 8 weeks after ACME’s
|
|
|
acceptance of the pre-series.\_
|
|
|
- §2.2 Deliverables Included in the Supply
|
|
|
The boards to be manufactured are fully described in the
|
|
|
Manufacturing File provided by ACME (see 4.3). This file,
|
|
|
downloadable from ACME’s Engineering Data Management System (EDMS),
|
|
|
contains Printed Circuit Board (PCB) information, parts lists,
|
|
|
component placement drawings, mechanical drawings and circuit
|
|
|
diagrams.
|
|
|
### Some extracts
|
|
|
|
|
|
\_This technical specification concerns the supply of 100 assembled and
|
|
|
tested ACME\_1 printed circuit boards, also known as EDA-02063 boards.
|
|
|
The delivery of the pre-series of 20 boards is required to be within 15
|
|
|
weeks following placement of the contract, while the remaining 80 boards
|
|
|
are required to be delivered within 8 weeks after ACME’s acceptance of
|
|
|
the pre-series.\_
|
|
|
|
|
|
*§2.2 Deliverables Included in the Supply**
|
|
|
The boards to be manufactured are fully described in the Manufacturing
|
|
|
File provided by ACME (see 4.3). This file, downloadable from ACME’s
|
|
|
Engineering Data Management System (EDMS), contains Printed Circuit
|
|
|
Board (PCB) information, parts lists, component placement drawings,
|
|
|
mechanical drawings and circuit diagrams.
|
|
|
The supply of the boards shall include:
|
|
|
- The purchase of the components and materials according to the
|
|
|
BOM;
|
|
|
- The manufacturing and assembly of the PCBs followed by testing;
|
|
|
- The manufacturing of mechanical parts;
|
|
|
- The assembly of the different parts;
|
|
|
- The final functional testing of the boards;
|
|
|
- The test results;
|
|
|
- The delivery to ACME (where included).
|
|
|
|
|
|
* The purchase of the components and materials according to the BOM;
|
|
|
|
|
|
* The manufacturing and assembly of the PCBs followed by testing;
|
|
|
|
|
|
* The manufacturing of mechanical parts;
|
|
|
|
|
|
* The assembly of the different parts;
|
|
|
|
|
|
* The final functional testing of the boards;
|
|
|
|
|
|
* The test results;
|
|
|
|
|
|
* The delivery to ACME (where included).
|
|
|
|
|
|
Please contact [Erik van der Bij](https://www.ohwr.org/users/9/), CERN
|
|
|
for details about this template.
|
|
|
|
|
|
-----
|
|
|
|
|
|
### Documentation required on delivery
|
|
|
|
|
|
Based on the technical specification that we use for Open Hardware
|
... | ... | @@ -58,5 +65,5 @@ the specification. |
|
|
|
|
|
-----
|
|
|
|
|
|
Erik van der Bij - 14 December 2015
|
|
|
Erik van der Bij - 7 January 2016
|
|
|
|