# 18 Mar 2020
|
|
|
|
|
|
## Crate Front Panel
|
|
|
- Even if the fact of having the crate-front-panel makes the mechanics more difficult and introduces a non-standard part (thicker separator to be able to screw the pcb) it was decided to move forward with this option and once a physical prototype is available check for possible modifications and moving it to the front.
|
|
|
|
|
|
## Upcoming schedule
|
|
|
- Friday 20/3 pm call to confirm models
|
|
|
- Monday 23/3 call to confirm deliverables
|
|
|
- Friday 27/3 project to be delivered
|
|
|
- Anna and the logistics team will then take over for the quotation and ordering the parts
|
|
|
|
|
|
# 13 Mar 2020
|
|
|
|
|
|
ACTIONS to be followed up by Creotech:
|
|
|
ACTIONS to be followed up by Creotech: <br>
|
|
|
|
|
|
Note: after pcb validation Creotech will need ~1.5 weeks to deliver crate designs/bom
|
|
|
|
|
|
- **ACTION A18** ask Schroff for divider plate 100mm
|
|
|
- **ACTION A20** Confirm the **rail for the Power Backplane** is the correct one for power supplies (there is a shift on the rail to accommodate the case) ->OK
|
|
|
|
|
|
- **ACTION A19** Have two executions: basic crate/ roof set
|
|
|
- **ACTION A18** ask Schroff for divider plate 100mm -> manufacture 100mm custom part and order schroff divider to test both
|
|
|
|
|
|
- **ACTION A20** Confirm the **rail for the Power Backplane** is the correct one for power supplies (there is a shift on the rail to accommodate the case)
|
|
|
- **ACTION A19** Have two executions: basic crate/ roof+feet set -> OK
|
|
|
|
|
|
- **ACTION A11d**: Use updated model of Schroff/ ELMA **Power Supply**
|
|
|
- **ACTION A11d**: Use updated model of Schroff/ ELMA **Power Supply** -> to resend models; talk on Friday to confirm models
|
|
|
|
|
|
- **ACTION A13**: Ensure no collisions with the POWER Backplane and the ELMA model! Here we have tested with a power-backplane-mechanical-prototype on the Schroff supply.
|
|
|
|
... | ... | @@ -20,13 +32,19 @@ Note: after pcb validation Creotech will need ~1.5 weeks to deliver crate design |
|
|
- BOM
|
|
|
- drawings of Schroff customised parts
|
|
|
- drawings of fully-customised (CTI) customised parts
|
|
|
-> talk on Monday 23/3 to finalise the design; next Friday final documentation; settle final price and data for the order
|
|
|
-> end of next week final product
|
|
|
-> quote will be available later
|
|
|
|
|
|
- **ACTION A7:** Autodesk model browser **descriptive names**: this is very time consuming and does not make sense to do it now that some parts are uncertain; for now we leave them like that and Kuba/Michal confirmed that in the end of the project they will be ok
|
|
|
-> yes for nxt Friday 27/3
|
|
|
|
|
|
- **ACTION A8:** Ask Schroff if the **following colors or similar** are available in metallic paint: <br>
|
|
|
**RAL5051, RAL4003, RAL9010**
|
|
|
-> forget for the moment; on a big order, at the moment of ordering schroff may find the color;)
|
|
|
|
|
|
- **ACTION A9:** Mikolaj has contacted **Anna for the BOM** purchase for the first prototype; he will follow up
|
|
|
-> from nxt Friday, 27/3 on
|
|
|
|
|
|
**PCBs validated:** <br>
|
|
|
- CPCIS-Backplane.step: https://ohwr.org/project/diot-crate-hw/blob/master/pcb/cpcis_backplane/CPCIS-Backplane.step <br>
|
... | ... | |