## Status
|
|
|
| **Date**| \* Event \*|
|
|
|
| 06-06-2013 | Start working on project |
|
|
|
| 16-06-2013 | First version of schematics and PCB component placement |
|
|
|
| 18-06-2013 | Schematic review |
|
|
|
| 22-06-2013 | Schematic bugs fixed, final component placement, start of PCB routing |
|
|
|
| 21-07-2013 | Board 100% routed. PCB review held |
|
|
|
| 30-07-2013 | PCB corrections applied, ready for production |
|
|
|
| 29-08-2013 | Assembled boards delivered, CPU works, Ethernet works|
|
|
|
## Status
|
|
|
|
|
|
<table>
|
|
|
<tbody>
|
|
|
<tr class="odd">
|
|
|
<td><strong>Date</strong></td>
|
|
|
<td><b> Event </b></td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>06-06-2013</td>
|
|
|
<td>Start working on project</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>16-06-2013</td>
|
|
|
<td>First version of schematics and PCB component placement</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>18-06-2013</td>
|
|
|
<td>Schematic review</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>22-06-2013</td>
|
|
|
<td>Schematic bugs fixed, final component placement, start of PCB routing</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>21-07-2013</td>
|
|
|
<td>Board 100% routed. PCB review held</td>
|
|
|
</tr>
|
|
|
<tr class="odd">
|
|
|
<td>30-07-2013</td>
|
|
|
<td>PCB corrections applied, ready for production</td>
|
|
|
</tr>
|
|
|
<tr class="even">
|
|
|
<td>29-08-2013</td>
|
|
|
<td>Assembled boards delivered, CPU works, Ethernet works, still waiting for new heatsink</td>
|
|
|
</tr>
|
|
|