WP8 Testing
Description
The work package 8 includes
- functional tests of the complete application (hw, gw, sw)
- tests over time
- tests under extreme conditions (ex. high temperature)
- EMC tests
The deliverables are
- thorough characterization of the performance of the masterFIP solution
The estimated duration is
- Eight manweeks
Outcome
- EMC tests
- Temperature & Consumption tests
- On going long runs in CHARM, QPS lab, FGC2 lab
E.Gousiou, July 2014