Complete status
Project status
Date | Activity |
---|---|
01/10/2011 | First sudies about necessities |
27/11/2011 | FMC standard choosed |
01/12/2011 | project stopped provisionally |
01/02/2012 | Discussion with FMC suppliers |
01/03/2012 | Commercial solution aborted=price vs desired features |
05/03/2012 | Project started at OHWR |
15/03/2012 | ADC choosed |
26/03/2012 | power dissipation solutions studied |
01/04/2012 | Clock frequency plan defined |
04/05/2012 | Specification document V1.0 done |
18/05/2012 | Discussions with OHWR companies about parallel development |
19/05/2012 | Discussions with Non OHWR companies about parallel development |
22/05/2012 | Start of block diagram design: clock schemes, PS, input stage,FMC interface,etc |
26/07/2012 | Many discussions with component manufacturers about details of implementation |
01/08/2012 | Start collaboration with WUT/Creotech for boards design (130 and 250 MSPS versions) |
22/10/2012 | Start schematics and discussions with WUT/Creotech |
22/11/2012 | Layout v1 70% done by LNLS - under revision and modification |
22/11/2012 | End of in-loco collaboration - layout sent to WUT/Creotech for refinements/layout optimization |
03/12/2012 | Decision of layout unification for reuse of heatsink in both boards |
06/12/2012 | Start of design modification, mechanical unification with FMC ADC 250M version |
19/12/2012 | Layout ready for review |
21/12/2012 | Fast review send from LNLS to WUT/Creotech |
01/01/2013 | Firmware verification and optimization to support the boards |
14/01/2013 | Bug found by OHWR user (7Solution) - power supply error in one IC |
30/01/2013 | Problems to find company to produce boards with some copper filled vias |
12/02/2013 | Pre-assembled boards received by WUT/Creotech |
14/02/2013 | Start basic tests |
26/02/2013 | Waiting for panels and heatsink - 2 weeks estimated |
20/03/2013 | Panels received |
30/03/2013 | Heatsinks received |
26/04/2013 | FMC ready, tested and assembled |
Filip Świtakowski - 29 Sep 2014