Examples of project planning Gantt charts
Development times
- Design and production time for Open Hardware designs (2013)
(pdf,
Excel)
- Conclusions
- V1 is not suitable for series production. Designs need usually two to four versions before being production ready.
- Highly resourced projects take two years from design start to series production. Others need almost three years.
- When components are provided by CERN, it usually still takes a company one year to produce a series. Pre-series are needed.
- Conclusions